Building Approval Process

When contemplating any type of building on your property, make the LCPOA your first stop. The Environmental and Architectural Committee (E & A) must first approve any structure before you begin building.

LCPOA building and temporary shed permit approval forms are available at the Lodge front desk during Lodge business hours.” (look in this newsletter for information on Lodge hours). For any building other than a shed, 2 sets of construction plans, 2 sets of plot plans plus 2 LCPOA approval forms are required to be submitted before the E&A can process the request. The E&A committee requires 10 days after the receipt of plans for approval for processing. If there are no problems with the request, (remember to include a telephone number on the application) one complete set of approved plans will be taken to the Rome Municipal Building within the 10 day period. The process of obtaining building permits from the Town and Adams County can then continue.